Back to projects

Ontario Street Watermain Upgrade

Schreiber, Ontario

completeDrinking WaterGIS
Federal contribution
$206,954
Federal share42%

of $493.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
2023
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Township of Schreiber
Construction start
May 23, 2023(actual)
Construction end
Aug 6, 2023(actual)

Also in Schreiber