Back to projects

Schreiber Community Park - Downtown Relocation

Schreiber, Ontario

completeActive TransportationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
2022
Built
Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Schreiber
Construction start
Oct 1, 2021(actual)
Construction end
Oct 6, 2022(actual)

Also in Schreiber

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60128 in the federal list. How to read these figures.