Schreiber Community Park - Downtown Relocation
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
2022
Built
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Schreiber
- Construction start
- Oct 1, 2021(actual)
- Construction end
- Oct 6, 2022(actual)
Also in Schreiber
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60128 in the federal list. How to read these figures.