Rehabilitation of Marlbank Road
Federal contribution
$469,187
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Tweed
- Construction start
- Jan 15, 2010(actual)
- Construction end
- Aug 27, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Nov 1, 2009
- Construction end2 months earlyforecast Oct 31, 2010
Also in Tweed
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30677 in the federal list. How to read these figures.