Installation of Louisa Street Second Watermain Crossing on Moira River

Tweed, Ontario

completeDrinking WaterGIS
Federal contribution
$404,800
Federal share40%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
2023
Built

Approved 6 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Municipality of Tweed
Construction start
Mar 18, 2022(actual)
Construction end
Sep 21, 2023(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Apr 18, 2022
  • Construction end3 months earlyforecast Dec 31, 2023