Installation of Louisa Street Second Watermain Crossing on Moira River
Federal contribution
$404,800
Federal share40%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
2023
Built
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Tweed
- Construction start
- Mar 18, 2022(actual)
- Construction end
- Sep 21, 2023(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Apr 18, 2022
- Construction end3 months earlyforecast Dec 31, 2023