Tweed Wastewater Lagoon System Upgrades
Federal contribution
$1.1M
$1,127,472
Federal share40%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 8, 2020
20212022
Built
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Tweed
- Construction start
- May 11, 2021(actual)
- Construction end
- Apr 30, 2022(actual)