completeWastewaterGIS
Federal contribution
$1.1M
$1,127,472
Federal share40%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 8, 2020
20212022
Built

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Municipality of Tweed
Construction start
May 11, 2021(actual)
Construction end
Apr 30, 2022(actual)