Road No. 503 Rehabilitation
Federal contribution
$371,803
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Haliburton
- Construction start
- Nov 20, 2009(actual)
- Construction end
- Dec 31, 2009(actual)
Against the original forecast
- Construction start3 months lateforecast Aug 10, 2009
- Construction end3 months lateforecast Oct 9, 2009
Also in Highlands East