Herlihey Park
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
2022202320242025
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Municipality of Highlands East
- Construction start
- Aug 10, 2023(actual)
- Construction end
- Aug 29, 2025(actual)
Against the original forecast
- Construction start11 months lateforecast Sep 12, 2022
- Construction end7 months earlyforecast Mar 31, 2026
Also in Highlands East
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59382 in the federal list. How to read these figures.