Haliburton Rail Trail Expansion
Federal contribution
$69,856
Federal share45%
of $156.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2009
2010
Built
Approved 2 months before the announcement.
- Program
- National Recreational Trails Program
- Ultimate recipient
- Ontario Federation of Trail Riders: OFTR
- Construction start
- May 26, 2009(actual)
- Construction end
- Mar 31, 2010(actual)
Also in Highlands East
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50915 in the federal list. How to read these figures.