Bolt Road Rehabilitation
Alfred and Plantagenet, Ontario
Federal contribution
$304,645
Federal share27%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Alfred and Plantagenet
- Construction start
- Aug 3, 2009(actual)
- Construction end
- Nov 18, 2009(actual)
Against the original forecast
- Construction start2 months lateforecast May 25, 2009
- Construction end5 weeks lateforecast Oct 15, 2009
Also in Alfred and Plantagenet
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30760 in the federal list. How to read these figures.