Bolt Road Rehabilitation

Alfred and Plantagenet, Ontario

completeHighways and RoadsISF
Federal contribution
$304,645
Federal share27%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 3, 2009(actual)
Construction end
Nov 18, 2009(actual)

Against the original forecast

  • Construction start2 months lateforecast May 25, 2009
  • Construction end5 weeks lateforecast Oct 15, 2009