Back to projects

Boundary Road Rehabilitation

Alfred and Plantagenet, Ontario

completeHighways and RoadsISF
Federal contribution
$209,497
Federal share24%

of $889.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 25, 2009(actual)
Construction end
Oct 27, 2009(actual)

Against the original forecast

  • Construction start2 months lateforecast May 25, 2009

Also in Alfred and Plantagenet

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30796 in the federal list. How to read these figures.