Stormwater Culvert Replacement Project - Village of Wendover

Alfred and Plantagenet, Ontario

completeWastewaterCWWF
Federal contribution
$206,363
Federal share20%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 8, 2017(actual)
Construction end
Sep 6, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 1, 2017
  • Construction end3 months lateforecast May 31, 2018