Stormwater Culvert Replacement Project - Village of Wendover
Alfred and Plantagenet, Ontario
Federal contribution
$206,363
Federal share20%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Alfred and Plantagenet
- Construction start
- Oct 8, 2017(actual)
- Construction end
- Sep 6, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 1, 2017
- Construction end3 months lateforecast May 31, 2018