Port Davidson Road Realignment
Federal contribution
$56,351
Federal share28%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of West Lincoln
- Construction start
- Apr 19, 2010(actual)
- Construction end
- Jun 30, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Apr 1, 2010
- Construction end9 months earlyforecast Mar 31, 2011
Also in West Lincoln
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31059 in the federal list. How to read these figures.