Replace and upgrade Thompson Road Sanitary Sewer to meet Growth Demand
Federal contribution
$45,000
Federal share50%
of $90.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of West Lincoln
- Construction start
- Nov 20, 2017(actual)
- Construction end
- Dec 15, 2017(actual)
Against the original forecast
- Construction start8 months lateforecast Apr 1, 2017
- Construction end5 months earlyforecast May 31, 2018