Back to projects

Rehabilitation of Public Works Building

West Lincoln, Ontario

completeVentilationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of West Lincoln
Construction start
May 5, 2021(actual)
Construction end
Sep 1, 2022(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Oct 1, 2022

Also in West Lincoln

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58928 in the federal list. How to read these figures.