Rural Road Upgrades
Federal contribution
$75,441
Federal share31%
of $240.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Sep 8, 2009(actual)
- Construction end
- Oct 23, 2009(actual)
Against the original forecast
- Construction start4 months lateforecast May 15, 2009
- Construction end11 months earlyforecast Sep 30, 2010
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31302 in the federal list. How to read these figures.