Garfield Material Recovery Facility Upgrades

East Gwillimbury, Ontario

completeSolid Waste ManagementISF
Federal contribution
$2.5M
$2,502,360
Federal share33%

of $7.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 20, 2010(actual)
Construction end
Jun 24, 2011(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 30, 2010
  • Construction end5 weeks earlyforecast Jul 29, 2011