Garfield Material Recovery Facility Upgrades
Federal contribution
$2.5M
$2,502,360
Federal share33%
of $7.6M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of York
- Construction start
- Aug 20, 2010(actual)
- Construction end
- Jun 24, 2011(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 30, 2010
- Construction end5 weeks earlyforecast Jul 29, 2011
Also in East Gwillimbury
- Emergency Medical Services Central Support Facility and Health Connection/Contact Centre$6.5M
- Holland Landing - Yonge St. Revitalization & Multi-Use Path Extension$3.8M
- East Gwillimbury Watermain Upgrades$2.0M
- Rehabilitation of the existing West Street Sewage Pumping Station to Improve the Efficiency of Wastewater Management$438.4K
- Administration Building Renovation$221.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31308 in the federal list. How to read these figures.