Rehabilitation of the existing West Street Sewage Pumping Station to Improve the Efficiency of Wastewater Management
Federal contribution
$438,408
Federal share40%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of East Gwillimbury
- Construction start
- Aug 25, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start7 months lateforecast Feb 1, 2017
- Construction end6 months lateforecast Oct 15, 2019
Also in East Gwillimbury