Emergency Medical Services Central Support Facility and Health Connection/Contact Centre
Federal contribution
$6.5M
$6,489,113
Federal share29%
of $22.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of York
- Construction start
- Dec 7, 2009(actual)
- Construction end
- Aug 15, 2011(actual)
Against the original forecast
- Construction start4 months earlyforecast Mar 31, 2010
- Construction end7 weeks earlyforecast Sep 30, 2011
Also in East Gwillimbury
- Holland Landing - Yonge St. Revitalization & Multi-Use Path Extension$3.8M
- Garfield Material Recovery Facility Upgrades$2.5M
- East Gwillimbury Watermain Upgrades$2.0M
- Rehabilitation of the existing West Street Sewage Pumping Station to Improve the Efficiency of Wastewater Management$438.4K
- Administration Building Renovation$221.9K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31905 in the federal list. How to read these figures.