Rural Road Upgrades
Federal contribution
$53,006
Federal share31%
of $170.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Oct 7, 2009(actual)
- Construction end
- Sep 22, 2010(actual)
Against the original forecast
- Construction start5 months lateforecast May 15, 2009
- Construction end5 weeks earlyforecast Oct 29, 2010
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31310 in the federal list. How to read these figures.