Rural Road Upgrades
Federal contribution
$41,605
Federal share20%
of $203.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- May 25, 2010(actual)
- Construction end
- Aug 4, 2010(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jun 14, 2010
- Construction end8 weeks earlyforecast Sep 30, 2010
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31325 in the federal list. How to read these figures.