French Hill Rural Road Upgrades
Federal contribution
$49,667
Federal share33%
of $149.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- May 28, 2010(actual)
- Construction end
- Sep 20, 2010(actual)