Back to projects

Rural Road Operational Improvements

Ottawa, Ontario

completeHighways and RoadsISF
Federal contribution
$124,860
Federal share30%

of $412.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Ottawa
Construction start
Oct 8, 2009(actual)
Construction end
Sep 30, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast May 15, 2009

Also in Ottawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31441 in the federal list. How to read these figures.