Rural Road Upgrades
Federal contribution
$26,064
Federal share30%
of $86.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jun 28, 2010(actual)
- Construction end
- Sep 23, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 14, 2010
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31516 in the federal list. How to read these figures.