Rural Road Upgrades
Federal contribution
$98,075
Federal share33%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jun 14, 2010(actual)
- Construction end
- Sep 30, 2011(actual)
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31522 in the federal list. How to read these figures.