Bearinger Road Corridor Improvements
Federal contribution
$570,116
Federal share32%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Waterloo
- Construction start
- Sep 28, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Sep 8, 2009
Also in Waterloo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31640 in the federal list. How to read these figures.