Bearinger Road Corridor Improvements

Waterloo, Ontario

completeHighways and RoadsISF
Federal contribution
$570,116
Federal share32%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Waterloo
Construction start
Sep 28, 2009(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Sep 8, 2009

Also in Waterloo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31640 in the federal list. How to read these figures.