Electric Buses

Waterloo, Ontario

completePublic TransitPTIS
Federal contribution
$4.7M
$4,669,907
Federal share40%

of $11.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 26, 2024
202320242025
Built

Approved 21 months before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Apr 29, 2022(actual)
Construction end
Feb 28, 2025(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 1, 2022
  • Construction end8 weeks lateforecast Dec 31, 2024

Also in Waterloo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63414 in the federal list. How to read these figures.