Purchase Voice Radio Infrastructure and Equipment to Be Installed in 300 Vehicles including Conventional Buses, Specialized Buses and Service Vehicles
Federal contribution
$4.6M
$4,595,523
Federal share50%
of $9.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2017
201820192020
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Waterloo
- Construction start
- Mar 27, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast Jan 1, 2017
- Construction end3 months lateforecast Dec 31, 2019
Also in Waterloo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49512 in the federal list. How to read these figures.