Hybrid Buses

Waterloo, Ontario

completePublic TransitPTIS
Federal contribution
$24.8M
$24,784,772
Federal share40%

of $62.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 17, 2025
2023202420252026
Built

Approved 3.7 years before the announcement.

Program
Public Transit Infrastructure Stream
Construction start
Apr 29, 2022(actual)
Construction end
Feb 28, 2025(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 1, 2022
  • Construction end10 months earlyforecast Dec 31, 2025

Also in Waterloo

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63415 in the federal list. How to read these figures.