Back to projects

County Road 16 Rehabilitation

Brant County, Ontario

completeHighways and RoadsISF
Federal contribution
$2.1M
$2,088,545
Federal share33%

of $6.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Brant
Construction start
Aug 17, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 15, 2009

Also in Brant County