Burford Administration Building Retrofits

Brant County, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$122,400
Federal share80%

of $153.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
County of Brant
Construction start
Oct 13, 2021(actual)
Construction end
Aug 8, 2022(actual)

Against the original forecast

  • Construction end6 weeks lateforecast Jun 30, 2022

Also in Brant County

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58932 in the federal list. How to read these figures.