HVAC upgrades at County of Brant facilities
Federal contribution
$64,800
Federal share80%
of $81.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- County of Brant
- Construction start
- Sep 29, 2021(actual)
- Construction end
- May 30, 2022(actual)
Against the original forecast
- Construction end4 weeks lateforecast Apr 29, 2022