Misener Road Bridge

Wainfleet, Ontario

completeHighways and RoadsISF
Federal contribution
$94,342
Federal share31%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 22, 2009
20102011
Built
Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Wainfleet
Construction start
May 12, 2010(actual)
Construction end
Dec 17, 2010(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Jun 15, 2010
  • Construction end2 weeks earlyforecast Dec 31, 2010

Also in Wainfleet

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31712 in the federal list. How to read these figures.