Rehabilitation of Lakeshore Road Storm Sewer

Wainfleet, Ontario

completeWastewaterGIS
Federal contribution
$255,568
Federal share41%

of $627.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 17, 2020
20212022
Built

Approved 4 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Township of Wainfleet
Construction start
Jun 13, 2022(actual)
Construction end
Oct 3, 2022(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 2, 2022

Also in Wainfleet

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 57312 in the federal list. How to read these figures.