Rehabilitation of Town Hall
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Wainfleet
- Construction start
- Sep 15, 2021(actual)
- Construction end
- Nov 26, 2021(actual)
Against the original forecast
- Construction start6 weeks lateforecast Aug 1, 2021
- Construction end5 weeks lateforecast Oct 21, 2021