Pinewood Place Reconstruction

Waterloo, Ontario

completeHighways and RoadsISF
Federal contribution
$185,829
Federal share33%

of $571.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Waterloo
Construction start
Sep 8, 2009(actual)
Construction end
Jun 30, 2010(actual)

Against the original forecast

  • Construction end3 months earlyforecast Sep 30, 2010