Road Resurfacing Program

Front of Yonge, Ontario

completeHighways and RoadsISF
Federal contribution
$180,307
Federal share33%

of $541.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Front of Yonge
Construction start
Aug 17, 2009(actual)
Construction end
Nov 30, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2009
  • Construction end4 weeks earlyforecast Dec 31, 2010