Upgrade Culverts, Ditching on Catholic Church Rd, 5 homes

Front of Yonge, Ontario

completeWastewaterCWWF
Federal contribution
$12,500
Federal share50%

of $25.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Front of Yonge
Construction start
Jun 26, 2017(actual)
Construction end
Aug 31, 2017(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 1, 2017
  • Construction end2 months earlyforecast Oct 31, 2017

Also in Front of Yonge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48775 in the federal list. How to read these figures.