Reconstruction and Drainage Improvements - Ballycanoe and Escott-Yonge Townline Road
Federal contribution
$134,466
Federal share33%
of $403.4K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Front of Yonge
- Construction start
- Oct 5, 2009(actual)
- Construction end
- Aug 27, 2010(actual)
Against the original forecast
- Construction start5 months earlyforecast Mar 21, 2010
- Construction end5 weeks earlyforecast Sep 30, 2010
Also in Front of Yonge
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32309 in the federal list. How to read these figures.