Reconstruction and Drainage Improvements - Ballycanoe and Escott-Yonge Townline Road

Front of Yonge, Ontario

completeHighways and RoadsISF
Federal contribution
$134,466
Federal share33%

of $403.4K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Front of Yonge
Construction start
Oct 5, 2009(actual)
Construction end
Aug 27, 2010(actual)

Against the original forecast

  • Construction start5 months earlyforecast Mar 21, 2010
  • Construction end5 weeks earlyforecast Sep 30, 2010

Also in Front of Yonge

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32309 in the federal list. How to read these figures.