Back to projects

Replacement of Polybutylene Service Connections - Love Crescent and Athabasca Street

Ajax, Ontario

completeDrinking WaterISF
Federal contribution
$46,573
Federal share33%

of $139.7K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 14, 2010(actual)
Construction end
Jan 6, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2010
  • Construction end10 months earlyforecast Oct 31, 2011

Also in Ajax