Back to projects

Fire Hall

Central Huron, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$435,000
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Oct 30, 2009(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Oct 1, 2009
  • Construction end4 weeks lateforecast Sep 30, 2011

Also in Central Huron

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31815 in the federal list. How to read these figures.