Fire Hall
Federal contribution
$435,000
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of Central Huron
- Construction start
- Oct 30, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Oct 1, 2009
- Construction end4 weeks lateforecast Sep 30, 2011
Also in Central Huron
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31815 in the federal list. How to read these figures.