Isaac Street Watermain Rehabilitation and Improvements
Federal contribution
$138,812
Federal share40%
of $347.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
20232024
Built
Approved 6 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of Central Huron
- Construction start
- May 17, 2023(actual)
- Construction end
- Apr 30, 2024(actual)
Against the original forecast
- Construction end6 months lateforecast Oct 31, 2023
Also in Central Huron
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62769 in the federal list. How to read these figures.