Mary Street sewer main rehabilitation and stormwater infiltration prevention

Central Huron, Ontario

completeWastewaterCWWF
Federal contribution
$56,198
Federal share50%

of $112.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Oct 2, 2017(actual)
Construction end
Jun 28, 2018(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 15, 2017
  • Construction end4 months lateforecast Mar 1, 2018