Replacement of Polybutylene Service Connections - Kipling Crescent and Pinehurst Avenue
Federal contribution
$64,831
Federal share26%
of $245.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Durham
- Construction start
- Oct 14, 2009(actual)
- Construction end
- Jan 6, 2011(actual)
Against the original forecast
- Construction start7 months earlyforecast May 1, 2010
- Construction end3 months earlyforecast Mar 31, 2011
Also in Ajax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31844 in the federal list. How to read these figures.