Replacement of Polybutylene Service Connections - Millinton Crescent and McClure Court
Federal contribution
$130,200
Federal share33%
of $390.6K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Durham
- Construction start
- Jul 19, 2010(actual)
- Construction end
- Jul 27, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jun 14, 2010
- Construction end3 months earlyforecast Oct 31, 2011
Also in Ajax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31850 in the federal list. How to read these figures.