Back to projects

Replacement of Polybutylene Service Connections - Vanessa Place

Whitby, Ontario

completeDrinking WaterISF
Federal contribution
$44,519
Federal share33%

of $134.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Apr 16, 2010(actual)
Construction end
May 14, 2010(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast Jun 11, 2010
  • Construction end4 months earlyforecast Aug 30, 2010

Also in Whitby

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31930 in the federal list. How to read these figures.