Replacement of Polybutylene Service Connections - Pinehurst Avenue

Whitby, Ontario

completeDrinking WaterISF
Federal contribution
$32,603
Federal share29%

of $111.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 19, 2010(actual)
Construction end
Jan 6, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 30, 2010
  • Construction end3 months earlyforecast Mar 31, 2011

Also in Whitby

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31937 in the federal list. How to read these figures.