Transitway Improvement Program - Blair Station
Federal contribution
$33,333
Federal share33%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jun 1, 2010(actual)
- Construction end
- Nov 12, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 1, 2010
- Construction end6 weeks lateforecast Oct 1, 2010