Drummond Road Reconstruction

Niagara Falls, Ontario

completeWastewaterISF
Federal contribution
$1.9M
$1,946,815
Federal share31%

of $6.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Niagara Falls
Construction start
Dec 7, 2009(actual)
Construction end
Aug 1, 2011(actual)

Against the original forecast

  • Construction end3 months earlyforecast Oct 31, 2011