Transitway Improvement Program - Hurdman Station
Federal contribution
$11,571
Federal share15%
of $75.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Aug 28, 2009(actual)
- Construction end
- Nov 1, 2010(actual)
Against the original forecast
- Construction start8 months earlyforecast May 1, 2010
- Construction end2 months lateforecast Sep 1, 2010