Integrated Road, Water and Sewer - Cambridge Street/Jackson Avenue/Frederick Place
Federal contribution
$823,052
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Ottawa
- Construction start
- Jun 21, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start5 weeks lateforecast May 20, 2010
Also in Ottawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31968 in the federal list. How to read these figures.